Grid code compliance focused on power factor and harmonic filtering
Gallery
Project overview
A study was carried out in the 23 kV power substation to detect the general values to verify compliance with the network code, where the study was later carried out in each of the distribution substations to size the harmonic filters and capacitor banks. The procurement, installation and commissioning of harmonic filters in 8 substations was carried out to raise the power factor and reduce harmonic currents.
- ClientHeineken Toluca
- Industry
- LocationToluca
- Year
Let’s build your solution together